Ind. Code § 8-23-1-22.5

Current through P.L. 171-2024
Section 8-23-1-22.5 - "Extraordinary cost"

"Extraordinary cost" means the cost to a utility to relocate existing facilities that is either:

(1) more than ten percent (10%) of the total operating revenue received by the utility during the utility's most recent full fiscal year; or
(2) more than fifty percent (50%) of the total estimated cost of a proposed highway or bridge construction or improvement project.

IC 8-23-1-22.5

As added by P.L. 63-1992, SEC.1.