Section 8-1.5-3-9 - Removal of utility from jurisdiction of commission for approval of rates and charges; procedure
(a) This subsection applies to a municipally owned utility that before June 1, 1987, was taken out of the jurisdiction of the commission for the approval of rates and charges. A utility to which this subsection applies is removed from the jurisdiction of the commission for approval of the issuance of stocks, bonds, notes, or other evidence of indebtedness.
(b) Except as provided in subsection (a), a municipal legislative body that wants to be taken out of the jurisdiction of the commission for approval of rates and charges and of the issuance of stocks, bonds, notes, or other evidence of indebtedness may submit the following public question to the registered voters of the municipality at the next election in the form prescribed by IC 3-10-9-4:

"Shall the municipally owned utility be taken out of the jurisdiction of the utility regulatory commission for approval of rates and charges and of the issuance of stocks, bonds, notes, or other evidence of indebtedness?".

(c) A municipal legislative body shall certify the public question to the county election board of the county that contains the greatest percentage of population of the municipality under IC 3-10-9-3 and submit the question under subsection (b) if it receives a petition that:
(1) is signed by at least the number of the registered voters of the municipality required under IC 3-8-6-3 to place a candidate on the ballot; and
(2) requests that the municipally owned utility be removed from the jurisdiction of the commission for approval of rates and charges and of the issuance of stocks, bonds, notes, or other evidence of indebtedness.
(d) If a majority of those voting favor taking the municipally owned utility out of the jurisdiction of the commission, the utility:
(1) is removed from the jurisdiction of the commission for approval of rates and charges and of the issuance of stocks, bonds, notes, or other evidence of indebtedness; and
(2) shall mail written notice of the withdrawal from commission jurisdiction to the commission within thirty (30) days after the utility's withdrawal.

IC 8-1.5-3-9

As added by Acts1982 , P.L. 74, SEC.1. Amended by P.L. 124-1987, SEC.1; P.L. 23-1988, SEC.62; P.L. 10-1988, SEC.217; P.L. 12-1995, SEC.101.