Ind. Code § 8-1-8.5-13

Current through P.L. 171-2024
Section 8-1-8.5-13 - Legislative findings; definitions; public utilities' annual resource planning report to commission; three-year forecast; contents; commission's review; investigation; order to acquire or construct resources; information in commission's annual report
(a) The general assembly finds that it is in the public interest to support the reliability, availability, and diversity of electric generating capacity in Indiana for the purpose of providing reliable and stable electric service to customers of public utilities.
(b) As used in this section, "appropriate regional transmission organization", with respect to a public utility, refers to the regional transmission organization approved by the Federal Energy Regulatory Commission for the control area that includes the public utility's assigned service area (as defined in IC 8-1-2.3-2).
(c) As used in this section, "capacity market" means an auction conducted by an appropriate regional transmission organization to determine a market clearing price for capacity based on the planning reserve margin requirements established by the appropriate regional transmission organization for a planning year with respect to which an auction has not yet been conducted.
(d) As used in this section, "fall unforced capacity", or "fall UCAP", with respect to an electric generating facility, means:
(1) the capacity value of the electric generating facility's installed capacity rate adjusted for the electric generating facility's average forced outage rate for the fall period, calculated as required by the appropriate regional transmission organization or by the Federal Energy Regulatory Commission;
(2) a metric that is similar to the metric described in subdivision (1) and that is required by the appropriate regional transmission organization; or
(3) if the appropriate regional transmission organization does not require a metric described in subdivision (1) or (2), a metric that:
(A) can be used to demonstrate that a public utility has sufficient capacity to:
(i) provide reliable electric service to Indiana customers for the fall period; and
(ii) meet its planning reserve margin requirement and other federal reliability requirements described in subsection (l)(4); and
(B) is acceptable to the commission.
(e) As used in this section, "MISO" refers to the regional transmission organization known as the Midcontinent Independent System Operator that operates the bulk power transmission system serving most of the geographic territory in Indiana.
(f) As used in this section, "planning reserve margin requirement", with respect to a public utility for a particular resource planning year, means the planning reserve margin requirement for that planning year that the public utility is obligated to meet in accordance with the public utility's membership in the appropriate regional transmission organization.
(g) As used in this section, "reliability adequacy metrics", with respect to a public utility, means calculations used to demonstrate all of the following:
(1) Subject to subsection (q)(2)(B), that the public utility:
(A) has in place sufficient summer UCAP; or
(B) can reasonably acquire not more than:
(i) thirty percent (30%) of its total summer UCAP from capacity markets, with respect to a report filed with the commission under subsection (l) before July 1, 2023; or
(ii) fifteen percent (15%) of its total summer UCAP from capacity markets, with respect to a report filed with the commission under subsection (l) after June 30, 2023;

such that it will have sufficient summer UCAP;

to provide reliable electric service to Indiana customers, and to meet its planning reserve margin requirement and other federal reliability requirements described in subsection (l)(4).

(2) Subject to subsection (q)(2)(B), that the public utility:
(A) has in place sufficient winter UCAP; or
(B) can reasonably acquire not more than:
(i) thirty percent (30%) of its total winter UCAP from capacity markets, with respect to a report filed with the commission under subsection (l) before July 1, 2023; or
(ii) fifteen percent (15%) of its total winter UCAP from capacity markets, with respect to a report filed with the commission under subsection (l) after June 30, 2023;

such that it will have sufficient winter UCAP;

to provide reliable electric service to Indiana customers, and to meet its planning reserve margin requirement and other federal reliability requirements described in subsection (l)(4).

(3) Subject to subsection (q)(2)(B), with respect to a report filed with the commission under subsection (l) after June 30, 2026, that the public utility:
(A) has in place sufficient spring UCAP; or
(B) can reasonably acquire not more than fifteen percent (15%) of its total spring UCAP from capacity markets, such that it will have sufficient spring UCAP;

to provide reliable electric service to Indiana customers, and to meet its planning reserve margin requirement and other federal reliability requirements described in subsection (l)(4).

(4) Subject to subsection (q)(2)(B), with respect to a report filed with the commission under subsection (l) after June 30, 2026, that the public utility:
(A) has in place sufficient fall UCAP; or
(B) can reasonably acquire not more than fifteen percent (15%) of its total fall UCAP from capacity markets, such that it will have sufficient fall UCAP;

to provide reliable electric service to Indiana customers, and to meet its planning reserve margin requirement and other federal reliability requirements described in subsection (l)(4).

(h) As used in this section, "spring unforced capacity", or "spring UCAP", with respect to an electric generating facility, means:
(1) the capacity value of the electric generating facility's installed capacity rate adjusted for the electric generating facility's average forced outage rate for the spring period, calculated as required by the appropriate regional transmission organization or by the Federal Energy Regulatory Commission;
(2) a metric that is similar to the metric described in subdivision (1) and that is required by the appropriate regional transmission organization; or
(3) if the appropriate regional transmission organization does not require a metric described in subdivision (1) or (2), a metric that:
(A) can be used to demonstrate that a public utility has sufficient capacity to:
(i) provide reliable electric service to Indiana customers for the spring period; and
(ii) meet its planning reserve margin requirement and other federal reliability requirements described in subsection (l)(4); and
(B) is acceptable to the commission.
(i) As used in this section, "summer unforced capacity", or "summer UCAP", with respect to an electric generating facility, means:
(1) the capacity value of the electric generating facility's installed capacity rate adjusted for the electric generating facility's average forced outage rate for the summer period, calculated as required by the appropriate regional transmission organization or by the Federal Energy Regulatory Commission; or
(2) a metric that is similar to the metric described in subdivision (1) and that is required by the appropriate regional transmission organization.
(j) As used in this section, "winter unforced capacity", or "winter UCAP", with respect to an electric generating facility, means:
(1) the capacity value of the electric generating facility's installed capacity rate adjusted for the electric generating facility's average forced outage rate for the winter period, calculated as required by the appropriate regional transmission organization or by the Federal Energy Regulatory Commission;
(2) a metric that is similar to the metric described in subdivision (1) and that is required by the appropriate regional transmission organization; or
(3) if the appropriate regional transmission organization does not require a metric described in subdivision (1) or (2), a metric that:
(A) can be used to demonstrate that a public utility has sufficient capacity to:
(i) provide reliable electric service to Indiana customers for the winter period; and
(ii) meet its planning reserve margin requirement and other federal reliability requirements described in subsection (l)(4); and
(B) is acceptable to the commission.
(k) A public utility that owns and operates an electric generating facility serving customers in Indiana shall operate and maintain the facility using good utility practices and in a manner:
(1) reasonably intended to support the provision of reliable and economic electric service to customers of the public utility; and
(2) reasonably consistent with the resource reliability requirements of MISO or any other appropriate regional transmission organization.
(l) Not later than thirty (30) days after the deadline for submitting an annual planning reserve margin report to MISO, each public utility providing electric service to Indiana customers shall, regardless of whether the public utility is required to submit an annual planning reserve margin report to MISO, file with the commission a report, in a form specified by the commission, that provides the following information for each of the next three (3) resource planning years, beginning with the planning year covered by the planning reserve margin report to MISO described in this subsection:
(1) The:
(A) capacity;
(B) location; and
(C) fuel source;

for each electric generating facility that is owned and operated by the electric utility and that will be used to provide electric service to Indiana customers.

(2) The amount of generating resource capacity or energy, or both, that the public utility has procured under contract and that will be used to provide electric service to Indiana customers, including the:
(A) capacity;
(B) location; and
(C) fuel source;

for each electric generating facility that will supply capacity or energy under the contract, to the extent known by the public utility.

(3) The amount of demand response resources available to the public utility under contracts and tariffs.
(4) The following:
(A) The planning reserve margin requirements established by MISO for the planning years covered by the report, to the extent known by the public utility with respect to any particular planning year covered by the report.
(B) If applicable, any other planning reserve margin requirement that:
(i) applies to the planning years covered by the report; and
(ii) the public utility is obligated to meet in accordance with the public utility's membership in an appropriate regional transmission organization;

to the extent known by the public utility with respect to any particular planning year covered by the report.

(C) Other federal reliability requirements that the public utility is obligated to meet in accordance with its membership in an appropriate regional transmission organization with respect to the planning years covered by the report, to the extent known by the public utility with respect to any particular planning year covered by the report.

For each planning reserve margin requirement reported under clause (A) or (B), the public utility shall include a comparison of that planning reserve margin requirement to the planning reserve margin requirement established by the same regional transmission organization for the 2021-2022 planning year.

(5) The reliability adequacy metrics of the public utility, as forecasted for the three (3) planning years covered by the report.
(m) Upon request by a public utility, the commission shall determine whether information provided in a report filed by the public utility under subsection (l):
(1) is confidential under IC 5-14-3-4 or is a trade secret under IC 24-2-3;
(2) is exempt from public access and disclosure by Indiana law; and
(3) shall be treated as confidential and protected from public access and disclosure by the commission.
(n) A joint agency created under IC 8-1-2.2 may file the report required under subsection (l) as a consolidated report on behalf of any or all of the municipally owned utilities that make up its membership.
(o) A:
(1) corporation organized under IC 23-17 that is an electric cooperative and that has at least one (1) member that is a corporation organized under IC 8-1-13; or
(2) general district corporation within the meaning of IC 8-1-13-23;

may file the report required under subsection (l) as a consolidated report on behalf of any or all of the cooperatively owned electric utilities that it serves.

(p) In reviewing a report filed by a public utility under subsection (l), the commission may request technical assistance from MISO or any other appropriate regional transmission organization in determining:
(1) the planning reserve margin requirements or other federal reliability requirements that the public utility is obligated to meet, as described in subsection (l)(4); and
(2) whether the resources available to the public utility under subsections (l)(1) through (l)(3) will be adequate to support the provision of reliable electric service to the public utility's Indiana customers.
(q) If, after reviewing a report filed by a public utility under subsection (l), the commission is not satisfied that the public utility can:
(1) provide reliable electric service to the public utility's Indiana customers; or
(2) either:
(A) satisfy both:
(i) its planning reserve margin requirement or other federal reliability requirements that the public utility is obligated to meet, as described in subsection (l)(4); and
(ii) the reliability adequacy metrics set forth in subsection (g); or
(B) provide sufficient reason as to why the public utility is unable to satisfy both:
(i) its planning reserve margin requirement or other federal reliability requirements that the public utility is obligated to meet, as described in subsection (l)(4); and
(ii) the reliability adequacy metrics set forth in subsection (g);

during one (1) more of the planning years covered by the report, the commission may conduct an investigation under IC 8-1-2-58 through IC 8-1-2-60 as to the reasons for the public utility's potential inability to meet the requirements described in subdivision (1) or (2), or both.

(r) If, upon investigation under IC 8-1-2-58 through IC 8-1-2-60, and after notice and hearing, as required by IC 8-1-2-59, the commission determines that the capacity resources available to the public utility under subsections (l)(1) through (l)(3) will not be adequate to support the provision of reliable electric service to the public utility's Indiana customers, or to allow the public utility to satisfy both its planning reserve margin requirements or other federal reliability requirements that the public utility is obligated to meet (as described in subsection (l)(4)) and the reliability adequacy metrics set forth in subsection (g), the commission shall issue an order directing the public utility to acquire or construct such capacity resources that are reasonable and necessary to enable the public utility to provide reliable electric service to its Indiana customers, and to satisfy both its planning reserve margin requirements or other federal reliability requirements described in subsection (l)(4) and the reliability adequacy metrics set forth in subsection (g). Not later than ninety (90) days after the date of the commission's order under this subsection, the public utility shall file for approval with the commission a plan to comply with the commission's order. The public utility's plan may include:
(1) a request for a certificate of public convenience and necessity under this chapter; or
(2) an application under IC 8-1-8.8;

or both.

(s) Beginning in 2022, the commission shall include in its annual report under IC 8-1-1-14 the following information:
(1) The commission's analysis regarding the ability of public utilities to:
(A) provide reliable electric service to Indiana customers; and
(B) satisfy both:
(i) their planning reserve margin requirements or other federal reliability requirements; and
(ii) the reliability adequacy metrics set forth in subsection (g);

for the next three (3) utility resource planning years, based on the most recent reports filed by public utilities under subsection (l).

(2) A summary of:
(A) the projected demand for retail electricity in Indiana over the next calendar year; and
(B) the amount and type of capacity resources committed to meeting the projected demand.

In preparing the summary required under this subdivision, the commission may consult with the forecasting group established under section 3.5 of this chapter.

(3) Beginning with the commission's annual report filed under IC 8-1-1-14 in 2025, the commission's analysis regarding the appropriate percentage or portion of:
(A) total spring UCAP that public utilities should be authorized to acquire from capacity markets under subsection (g)(3)(B); and
(B) total fall UCAP that public utilities should be authorized to acquire from capacity markets under subsection (g)(4)(B).
(t) The commission may adopt rules under IC 4-22-2 to implement this section.

IC 8-1-8.5-13

Amended by P.L. 93-2024,SEC. 68, eff. 7/1/2024.
Amended by P.L. 55-2023,SEC. 6, eff. 7/1/2023.
Added by P.L. 60-2021,SEC. 2, eff. 7/1/2021.