Ind. Code § 8-1-40-19

Current through P.L. 171-2024
Section 8-1-40-19 - Electricity supplier's petition to commission for recovery of energy delivery costs attributable to distributed generation customers; approval; findings by commission
(a) To ensure that customers that produce distributed generation are properly charged for the costs of the electricity delivery system through which an electricity supplier:
(1) provides retail electric service to those customers; and
(2) procures excess distributed generation from those customers;

the electricity supplier may request approval by the commission of the recovery of energy delivery costs attributable to serving customers that produce distributed generation.

(b) The commission may approve a request for cost recovery submitted by an electricity supplier under subsection (a) if the commission finds that the request:
(1) is reasonable; and
(2) does not result in a double recovery of energy delivery costs from customers that produce distributed generation.

IC 8-1-40-19

Added by P.L. 264-2017,SEC. 6, eff. 7/1/2017.