Current through P.L. 171-2024
Section 8-1-40-19 - Electricity supplier's petition to commission for recovery of energy delivery costs attributable to distributed generation customers; approval; findings by commission(a) To ensure that customers that produce distributed generation are properly charged for the costs of the electricity delivery system through which an electricity supplier: (1) provides retail electric service to those customers; and(2) procures excess distributed generation from those customers; the electricity supplier may request approval by the commission of the recovery of energy delivery costs attributable to serving customers that produce distributed generation.
(b) The commission may approve a request for cost recovery submitted by an electricity supplier under subsection (a) if the commission finds that the request: (2) does not result in a double recovery of energy delivery costs from customers that produce distributed generation.Added by P.L. 264-2017,SEC. 6, eff. 7/1/2017.