The additional basis points authorized by the commission under this subsection for each CPS goal period are not cumulative. In determining a participating electricity supplier's authorized rate of return to which additional basis points may be added upon the participating electricity supplier's achievement of a particular CPS goal, the commission shall not include as part of the authorized rate of return any additional basis points awarded to the participating electricity supplier for having achieved the immediately preceding CPS goal.
For purposes of this subsection and subsection (h)(1), "program costs" includes administrative costs, ancillary costs, capacity costs, costs associated with CECs, capital costs, depreciation costs, tax costs, and financing costs incurred in connection with an activity described in subdivision (1) or (2).
for approval for the incentive or periodic rate adjustment mechanism sought.
IC 8-1-37-13