that will involve an excavation or demolition operation described in section 14 of this chapter may voluntarily, before commencing preliminary engineering studies or construction planning activities in the project area that will be affected by the excavation or demolition, serve a design information notice on the association of the person's intent to conduct the preliminary engineering studies or construction planning activities. However, not more than two (2) design information notices for the same project and from the same person or source may be submitted in any given one hundred eighty (180) day period.
A person responsible for conducting the preliminary engineering studies or construction planning activities may commence work before the elapse of ten (10) full working days if all affected operators have notified the person providing the design information notice that the location of all the affected operators' facilities have been marked or that the affected operators have no facilities in the project area that will be affected by the proposed excavation or demolition.
to inspect, at a location that is acceptable to the operator, drawings or other records for all of the operator's underground facilities within the project area that will be affected by the proposed excavation or demolition.
pending the operator obtaining additional information concerning the legitimacy of the design information notice. If an operator rejects a design information notice under this subsection, the operator shall provide notice of the rejection to, and may request additional information from, the person serving the design information notice.
IC 8-1-26-16.5