Section 5-32-3-7 - CMc performance of work

A CMc may perform a part of the work only if:

(1) the public agency approves of the CMc's performance of the work;
(2) the CMc would be awarded a contract for the work under the applicable contract award standard; and
(3) the CMc performs only such work that equals not more than twenty percent (20%) of the total value of the project.

IC 5-32-3-7

Added by P.L. 128-2014, SEC. 1, eff. 7/1/2014.