with respect to any particular commercial solar project that is approved under the unit's commercial solar regulation, for a period of at least ten (10) years, beginning with the start date of the commercial solar project's full commercial operation.
the office may authorize the unit to receive from the fund, for a period of ten (10) years beginning with the start date of the commercial solar project's full commercial operation, one dollar ($1) per megawatt hour of electricity generated by the commercial solar project, if the office determines that the procedures and standards set forth in the unit's commercial solar regulation were adhered to in the development of the project. However, if the office determines at any time after the start of the commercial solar project's full commercial operation that the unit has failed to continue to meet the requirement for certification set forth in subsection (a)(3), the office shall discontinue the incentive granted under this subsection and shall require the unit to return to the fund any amounts collected by the unit under this subsection after the unit's breach of the requirement for certification set forth in subsection (a)(3).
the project owner shall annually report to the office the total megawatt hours generated by the commercial solar energy facility in the previous year.
IC 4-3-23.1-13