may have a lien as set forth in this section.
to the extent of the value of any labor done or the material furnished, or both, including any use of the leased equipment and tools.
located in or about the shop, mill, wareroom, storeroom, manufactory or other building, bridge, reservoir, system of waterworks, or other structure, sidewalk, walk, stile, well, drain, drainage ditch, sewer, cistern, or earth used in a business.
regulated under IC 8; and
may include a provision or stipulation in the contract of the owner and principal contractor that a lien may not attach to the real estate, building, structure or any other improvement of the owner.
A contract containing a provision or stipulation described in subsection (e) does not affect a lien for labor, material, or machinery supplied before the filing of the contract with the recorder.
in books kept for that purpose; and
must furnish to the occupying owner of the parcel of land where the material, labor, or machinery is delivered a written notice of the delivery or work and of the existence of lien rights not later than thirty (30) days after the date of first delivery or labor performed. The furnishing of the notice is a condition precedent to the right of acquiring a lien upon the lot or parcel of land or the improvement on the lot or parcel of land.
with a written notice of the delivery or labor and the existence of lien rights not later than sixty (60) days after the date of the first delivery or labor performed; and
The furnishing and filing of the notice is a condition precedent to the right of acquiring a lien upon the real estate or upon the improvement constructed on the real estate.
IC 32-28-3-1
Pre-2002 Recodification Citation: 32-8-3-1.