Ind. Code § 25-1-21-9

Current through P.L. 171-2024
Section 25-1-21-9 - Board final approval

Notwithstanding any other law, if a board has a pending application for initial licensure or certification that requires final approval by the board, the board shall meet not more than thirty-one (31) days after the application is ready for approval.

IC 25-1-21-9

Added by P.L. 149-2022,SEC. 2, eff. 3/18/2022.