Current through P.L. 171-2024
Section 14-34-5-5 - Revision of permit(a) During the term of the permit, the permittee may submit an application for a revision of the permit, together with a revised reclamation plan, to the director. However, except for incidental boundary revisions, a new permit is required for any extensions to the permit area.(b) The director may not approve an application for a permit revision unless the director finds the following:(1) Reclamation required by this article can be accomplished under the revised reclamation plan.(2) The permittee has complied with:(A) IC 13-4.1-4 (before its repeal); or(c) The director shall establish guidelines for a determination of the scale or extent of a revision request for which all permit application information requirements and procedures apply.Pre-1995 Recodification Citation: 13-4.1-5-5.
As added by P.L. 1-1995, SEC.27.