Current through P.L. 171-2024
Section 13-18-16-5 - Approval of plans Plans and specifications submitted to the commissioner under section 1 of this chapter shall be approved if it is determined that the plans and specifications meet all of the following conditions:
(1) The plans and specifications are satisfactory with respect to the following: (A) Sanitary quality, including chlorination, if required.(C) Adequacy of the water supply.(2) The plans and specifications meet the requirements of any rules or standards adopted by the board under section 8 of this chapter governing the location, design, construction, and operation and maintenance of: (A) public water system installations; and(B) changes or additions to public water system installations.Pre-1996 Recodification Citation: 13-7-14-2.
As added by P.L. 1-1996, SEC.8. Amended by P.L. 184-2002, SEC.15.