735 ILCS 30/25-7-103.81

Current through Public Act 103-1052
Section 735 ILCS 30/25-7-103.81 - Quick-take; County of Lake

Quick-take proceedings under may be used for a period of 24 months after July 30, 1999, by the County of Lake, for the acquisition of necessary right-of-way to complete the improvement of the various intersections and roadways involved in the project to improve County Highway 70 (Hawley Street), County Highway 26 (Gilmer Road), and County Highway 62 (Fremont Center Road) at and near Illinois Route 176.

735 ILCS 30/25-7-103.81

Added by P.A. 094-1055,§ 25-7-103.81, eff. 1/1/2007.