Section 65 ILCS 5/11-135.5-65 - Small projects

In any case where the total overall cost of the project is estimated to be less than $12,000,000, the commission may combine the two-phase procedure for selection described in Section 11-135.5-60 into one combined step, provided that all the requirements of evaluation are performed in accordance with Section 11-135.5-60.

65 ILCS 5/11-135.5-65

Added by P.A. 102-1134,§ 5, eff. 2/10/2023.