30 ILCS 537/35

Current through Public Act 103-1052
Section 30 ILCS 537/35 - [Section Scheduled to be Repealed Effective 7/1/2026] Small projects

In any case where the total overall cost of the project is estimated to be less than $10 million, the State construction agency may combine the two-phase procedure for selection described in Section 30 into one combined step, provided that all the requirements of evaluation are performed in accordance with Section 30.

30 ILCS 537/35

Added by P.A. 094-0716, § 35, eff. 12/13/2005.