Conn. Gen. Stat. § 48-6
(1949 Rev., S. 7179; 1959, P.A. 152, S. 64; 1961, P.A. 294; 1971, P.A. 198; P.A. 83-587, S. 58, 96; P.A. 91-398, S. 3, 7; P.A. 95-340, S. 5; P.A. 07-141, S. 20.)
Cited. 100 C. 411. Challenge of authority's decision must be by procedures under Sec. 48-12. 154 C. 446. Cited. 186 C. 229. Cited. 23 CA 554; 32 CA 611. 6-month time limitation in Subsec. (a) applies only to condemnation proceedings and not to voluntary sales. 94 CA 364. Where referendum question stated that property proposed to be acquired by eminent domain by municipality for a school project would also be used for open space and general government, provisions of section requiring commencement of compensation process within 6 months of referendum apply. 103 CA 369. Establishment of an airport by a town is clearly one of its municipal purposes and proceedings to condemn for such are brought under this section and Sec. 48-12. 9 CS 317. Cited. 20 Conn.Supp. 422.