not later than thirty days after the receipt of any certificate of need application. Such hearing shall be held at the facility for which the certificate of need application was submitted. The commissioner or the commissioner's designee shall provide both the facility and the public with notice of the date of the hearing not less than ten days in advance of such date. Notice to the facility shall be sent via electronic mail or first-class mail and notice to the public shall be by publication in a newspaper having a substantial circulation in the area served by the facility. The provisions of this subsection shall not apply to any certificate of need approval requested for the relocation of a facility, or a portion of a facility's licensed beds, to a new or replacement facility.
Conn. Gen. Stat. § 17b-353
( P.A. 93-262, S. 21, 87; P.A. 94-236, S. 1, 10; P.A. 95-257, S. 39, 58; P.A. 97-112, S. 2; June 18 Sp. Sess. P.A. 97-2, S. 147, 165; P.A. 02-135, S. 1; June 30 Sp. Sess. P.A. 03-3, S. 78; P.A. 07-73, S. 2 (a); P.A. 10-179, S. 98; P.A. 13-139, S. 12; P.A. 16-8, S. 1; June Sp. Sess. P.A. 17-2, S. 182, 310; P.A. 18-91, S. 70; 18-169, S. 34.)