An application for a permit for any proposed work shall be deemed to have been abandoned six months after the date of filing, unless the application has been diligently prosecuted or a permit shall have been issued; except that for reasonable cause, the building official may grant one or more extensions for additional periods of time not exceeding ninety (90) days each.
R.I. Gen. Laws § 23-27.3-113.9