D.C. Code § 40-303.10

Current through codified legislation effective April 20, 2024
Section 40-303.10 - Subcontractor preferred to contractor

If the original contractor and the persons contracting or employed under him shall both have filed notices of liens, as aforesaid, the latter shall first be satisfied out of the proceeds of sale before the original contractor, but not in excess of the amount due him, and the balance, if any, of said amount shall be paid to him.

D.C. Code § 40-303.10

Mar. 3, 1901, 31 Stat. 1386, ch. 854, § 1248.