Category Category Total Subcategory Subcategory Weight Facility Condition 0.55 Date and type of last major construction through the preceding fiscal year 0.20 Expenditures for major construction projects for the preceding 10 fiscal years per square feet of the school facility 0.15 School facility condition score based on the most recent assessment completed by the Department of General Services 0.20 Demand 0.20 Average percentage of the school's enrollment growth over the past 5 school years based on audited enrollment 0.10 Average percent of school facility's building utilization over the past 5 school years 0.10 Community Need 0.10 Number of in-boundary children who would be served by the school facility's educational program divided by the school facility's capacity 0.05 Projected percent change in the number of children who would be served by the school facility's educational program in the neighborhood cluster over a prospective 6-year time period 0.05 Equity 0.15 Total number of square feet in the school's feeder pattern that have had a major construction in the preceding 10 fiscal years divided by total square footage of the feeder pattern 0.05 Number of at-risk students enrolled in the school based on the current school year enrollment projection 0.10
D.C. Code § 38-2803
Section 3 of D.C. Law 23-33 provided that notwithstanding subsection (a)(1) of this section, the DC Public Education Master Facilities Plan 2018, submitted by the Mayor to the Council of the District of Columbia on March 15, 2019, is disapproved.
Section 3 of D.C. Act 23-108 provided that notwithstanding subsection (a)(1) of this section, the DC Public Education Master Facilities Plan 2018, submitted by the Mayor to the Council of the District of Columbia on March 15, 2019, is disapproved.
Section 4112 of D.C. Law 18-223 provided:
"Sec. 4112. (a) Pursuant to section 1104 of the School Based Budgeting and Accountability Act of 1998, approved March 26, 1999 (D.C. Law 12-175; D. C. Official Code § 38-2803 ), the following components of the Master Facilities Plan for the District of Columbia Public Schools for 2010, as submitted by the Mayor to the Council, on April 1, 2010 ( ~2010 MFP') are approved:
"(1) All priorities, objectives, and methods of defining modernization, including the phased approach to elementary and middle schools;
"(2) Demographics and Data;
"(3) Plan Detail Narrative, including school-by-school detail, known as Mini-Master Plans; and
"(4) The glossary of terms.
"(b) The Schedule of modernization, including sequencing and project implementation timelines and the budget, including the 8-Year Master Facilities Plan Financial Projection and Scope of Work and Estimated Methodology in the 2010 MFP shall be adjusted pursuant to the Capital Improvement Plan Amendments for Public Education Facilities Act of 2010, passed on 2nd reading on June 15, 2010 (Enrolled version of Bill 18-731), and resubmitted by October 15, 2010, to the Council for review and approval."
Section 4082 of D.C. Law 20-61 provided that the Council approves the 2013 Master Facilities Plan for public education facilities submitted by the Mayor on March 28, 2013.
Applicability
Section 7025 of D.C. Law 22-33 repealed § 3 of D.C. Law 21-219. Therefore the changes made to this section by D.C. Law 21-219 have been implemented.
Applicability of D.C. Law 21-219: § 3 of D.C. Law 21-219 provided that the change made to this section by § 2(b) of D.C. Law 21-219 is subject to the inclusion of the law's fiscal effect in an approved budget and financial plan. Therefore that amendment has not been implemented.