Del. Code tit. 7 § 6098

Current through 2024 Legislative Session Act Chapter 531
Section 6098 - Application shield

Except for sources required to have a permit before construction or modification under the applicable requirements of this subchapter, if an applicant has submitted a timely and complete application for a permit required by this title (including renewals), but final action has not been taken on such application, the source's failure to have a permit shall not be a violation of this subchapter, unless the delay in final action was due to the failure of the applicant to timely submit information required or requested to process the application.

7 Del. C. § 6098

Amended by Laws 2013, ch. 430,s 2, eff. 9/11/2014.
72 Del. Laws, c. 214, § 3.;