Md. Code, Pub. Safety § 12-605

Current with changes from the 2024 Legislative Session effective on or before 7/1/2024, from Chs.. 2 through 1049
Section 12-605 - Electrical inspection certificates
(a) Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut-in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.
(b) Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.

Md. Code, PS § 12-605