Section 7-106 - Permit - Prerequisites for issuance

As a prerequisite to the issuance of a facility permit, the Department shall require an applicant:

(1) To provide evidence of financial ability to properly establish, operate, and maintain a facility;
(2) To file with the Department acceptable evidence of a bond or other security that the Department requires under § 7-111 of this subtitle;
(3) To agree to permit access to the facility for the purposes of any inspection permitted or required under this subtitle; and
(4) To pay the permit fee assessed under § 7-107 of this subtitle.