S.C. Code § 11-35-835

Current through 2024 Act No. 209.
Section 11-35-835 - Office of State Engineer to review completed documents within specified time

The Office of State Engineer must review properly completed schematic design, properly completed design development, and properly completed construction documents within a total of forty-five days of submission of documents.

S.C. Code § 11-35-835

1997 Act No. 153, Section 1; 1993 Act No. 178, Section 17.