If the department shall find that any map or plan of any coal mine made or furnished in pursuance of the provisions of this article is materially incomplete, inaccurate, or imperfect, then it may cause a correct survey and map or plan of said mine to be made at the expense of the operator thereof, the cost of which shall be recoverable from said operator as other debts are recoverable by law. When the department shall cause a new survey and map or plan of such coal mine and it is found that the map or plan furnished by the operator was substantially correct, then the cost of the survey, map, or plan caused to be made by the department shall be paid by the state.
Ala. Code § 25-9-302 (1975)