Cal. Civ. Code § 8186

Current through the 2023 Legislative Session.
Section 8186 - Recording notice of completion if improvement made pursuant to two or more direct contracts

If a work of improvement is made pursuant to two or more direct contracts, each covering a portion of the work of improvement:

(a) The owner may record a notice of completion of a direct contract for a portion of the work of improvement. On recordation of the notice of completion, for the purpose of Sections 8412 and 8414, a direct contractor is deemed to have completed the contract for which the notice of completion is recorded and a claimant other than a direct contractor is deemed to have ceased providing work.
(b) If the owner does not record a notice of completion under this section, the period for recording a claim of lien is that provided in Sections 8412 and 8414.

Ca. Civ. Code § 8186

Added by Stats 2010 ch 697 (SB 189),s 20, eff. 1/1/2011, op. 7/1/2012.