Current through Chapter 61 of the 2024 Legislative Session and 2024 Executive Orders 125, 133 through 135
Section 36.30.625 - Appeal on a contract claim(a) An appeal from a decision of the procurement officer on a contract claim may be filed by the contractor with the commissioner of administration or, for a claim involving a construction contract, lease of space, or procurement for the state equipment fleet, the commissioner of transportation and public facilities. The appeal shall be filed within 14 days after the decision is received by the contractor. An appeal by a contractor of the Department of Transportation and Public Facilities may not raise any new factual issues or theories of recovery that were not presented to and decided by the procurement officer in the decision under AS 36.30.620 (b), except that a contractor may increase the contractor's calculation of damages if the increase arises out of the same operative facts on which the original claim was based. The contractor shall file a copy of the appeal with the procurement officer.(b) An appeal must contain a copy of the decision being appealed and identification of the factual or legal errors in the decision that form the basis for the appeal.(c) The Department of Transportation and Public Facilities, or a contracting agency to whom the responsibility for handling the claim is delegated by the Department of Transportation and Public Facilities under AS 36.30.632, shall handle the appeal of a claim under this section expeditiously.Amended by AK 2022 Executive Order 122,sec. 29, eff. 7/1/2022.