Section 09.45.884 - Consequence of rejecting inspection or settlement offer
(a) If the claimant rejects the inspection offer under AS 09.45.882(b)(1) or the settlement offer under AS 09.45.882(b)(2), the claimant shall serve written notice of the claimant's rejection on the construction professional.
(b) The notice under (a) of this section must include the basis for the claimant's rejection of the construction professional's offer.
(c) After service of the rejection notice required by (a) of this section, the claimant may bring an action against the construction professional for the claim described in the notice of claim made under AS 09.45.881 without further notice.