(a) Responsibilities of the Contractor: - (i) Contractor compiles a comprehensive list of Wyoming expenditures and calculates qualified percentage rebate within sixty (60) days of completing principal photography.
- (ii) In compliance with the Production Rebate Agreement, the Contractor provides proof of the following:
- (A) Total dollar amount spent in Wyoming (including labor);
- (B) Total Wyoming payroll figure;
- (C) Total number of Wyoming crew members hired;
- (D) Average crew size (per day) for prep and shoot;
- (E) Prep dates & number of prep days;
- (F) Shoot dates & number of shoot days; and
- (G) List of all Wyoming cities/towns used for locations.
(b) Responsibilities of the Council: - (i) Wyoming Film Office confirms compliance with the Production Rebate Agreement and verifies percentage rebate figures.
- (ii) Council Comptroller's Office verifies Film Industry Financial Incentive (FIFI) funds, voucher processing and reimbursement of rebate.