(a) Costs for preparation or presentation of loan application;
(b) Costs incurred prior to loan award, except costs incurred for architectural and engineering design, surveying and environmental review, if required;
(c) Engineering fees, including design, inspection and contract administration costs, in excess of fifteen percent (15%) of project cost;
(d) Markups by engineers/architects of sub-contractor and other outside charges;
(e) Costs for transportation, meals, lodging and incidentals incurred offsite from the project or that exceed the current federal per diem reimbursement rate;
(f) Costs associated with the borrower's own employees and equipment;
(g) Costs for real property in excess of current fair market value and/or costs for an amount of real property in excess of that needed for project purposes;
(h) Costs related to issuance of bonds;
(i) Costs for furnishings;
(j) Legal fees;
(k) Costs for sidewalks that are owned or maintained by a private property owner; and,
(l) Costs for contingency or extra work allowance in excess of 10% of estimated construction costs.
060-38 Wyo. Code R. § 38-10
Adopted, Eff. 11/13/2018.