054-6 Wyo. Code R. § 6-8

Current through April 27, 2019
Section 6-8 - Site Visit Conducted by the Board

(a) Pre-Site Visit Process.

  • (i) At least three (3) months prior to the site visit, the Board shall notify the program of the site visit.
  • (ii) Thirty (30) days prior to the scheduled site visit, the program shall submit the self-study evaluation or plan of correction to the Board.
  • (iii) The program shall schedule all site visit activities.

(b) Post Site Visit Report.

  • (i) Following a site visit, the Board shall provide a report of its findings to the program.
  • (ii) The program may respond to the report with additional information within ninety (90) days.
  • (iii) Following review of the program's response, the Board shall issue a final decision. Written notification of the final decision shall be sent to the parent institution and the administrator.

054-6 Wyo. Code R. § 6-8

Amended, Eff. 4/12/2016.