(a) Wyoming Statute 1 -26-813 requires that permission be obtained from the Department prior to constructing any utility facilities along, across, or under the streets, roads, and highways under Department jurisdiction.
(b) The Department has developed a license form and a license agreement, as well as requirements for an exhibit showing what the applicant proposes to construct on the highway right-of-way and where this facility is to be located.
(c) The Department has also developed a Joint Occupancy Agreement for those instances where a utility facility with prior rights may be located within the highway right-of-way.
(d) An Exhibit (Drawing) of the facility's location within the highway right-of-way is required.
(e) The licenses and any agreements executed between the Department and a utility which refer to or authorize occupancy of highway R/W become a permanent part of the Department files and will be used on future highway projects to determine whether a reimbursement is due the utility for relocation.
045-5 Wyo. Code R. § 5-1