029-7 Wyo. Code R. § 7-6

Current through April 27, 2019
Section 7-6 - Evaluation

The Commission shall evaluate applications by considering the following:

(a) Information submitted in the project application;

(b) Whether the Applicant is current on all repayment obligations to the State;

(c) General program emphasis; and

(d) Whether the Applicant completed the most recent Commission public water system survey or irrigation system survey.

(e) For construction projects, the Commission shall consider the following additional factors:

  • (i) Whether the Applicant completed the necessary level of planning studies to adequately define the project scope, assess feasibility, evaluate alternatives, and determine probable costs;
  • (ii) Whether the Applicant presented an adequate financial plan to fund the project;
  • (iii) Whether the Applicant is prepared to establish an adequate operations and maintenance account;
  • (iv) Whether the Applicant is ready to proceed with construction, implementation, and operations; and
  • (v) Whether the Applicant is prepared to operate and maintain the project.

(f) For rehabilitation projects, the Commission shall also consider the Applicant's past efforts in adequately maintaining the project and whether the Applicant has an existing maintenance account.

029-7 Wyo. Code R. § 7-6

Adopted, Eff. 11/27/2017.