023-3 Wyo. Code R. § 3-22

Current through April 27, 2019
Section 3-22 - Construction Reports

Each utility issued a certificate of public convenience and necessity for a specific project or extension shall:

(a) Report the date construction will commence as soon as it is known, but no later than five business days prior to commencement;

(b) Submit monthly construction progress reports;

(c) Report the date construction was completed within 20 business days of completion; and

(d) Submit a report no later than 180 days following completion of construction that includes:

  • (i) Name of project;
  • (ii) Date in service;
  • (iii) Labor costs;
  • (iv) Material costs by general category;
  • (v) Administrative and general expenses;
  • (vi) Engineering costs;
  • (vii) Right-of-way costs;
  • (viii) Costs and rates used to calculate Allowance for Funds Used During Construction;
  • (ix) Other costs for which the utility will seek recovery for in rates and how items (iii) through (vii) were accounted for in its books and records;
  • (x) Proposed depreciation rates;
  • (xi) Journal entries transferring the completed project from Construction Work in Progress to Utility Plant in Service by account number;
  • (xii) For facility modifications, journal entries recording any plant retired and appropriate account numbers for utility plant and reserve for depreciation;
  • (xiii) For facility modifications, journal entries recording any plant salvage values and decommissioning costs or sale of any plant retired;
  • (xiv) Contact information for contractors that performed work;
  • (xv) Conditions (terrain, location, weather, etc.) under which construction was performed;
  • (xvi) Any non-standard facility feature; and
  • (xvii) Completed project maps and engineering drawings, if changed from those previously submitted.

023-3 Wyo. Code R. § 3-22

Adopted, Eff. 3/21/2016.

Amended, Eff. 4/8/2019.