020-2 Wyo. Code R. § 2-14

Current through April 27, 2019
Section 2-14 - Continuances and Extensions of Time

(a) A motion for a continuance of any scheduled hearing shall be in writing, state the reasons for the motion, and be filed and served on all parties and the hearing officer. A motion for a continuance shall be granted only upon a showing of good cause.

(b) A motion for an extension of time for performing any act prescribed or allowed by these rules or by order of the hearing officer shall be filed and served on all parties and the hearing officer prior to the expiration of the applicable time period. A motion for extension of time shall be granted only upon a showing of good cause.

(c) For contested cases conducted regarding objections pursuant to W.S. 35-11-406(k), a motion for continuance may not be granted if the motion would continue the hearing beyond the 20-day period provided in that statute unless the parties stipulate to a different period.

020-2 Wyo. Code R. § 2-14

Amended, Eff. 4/24/2017.