Section TCS 12.05 - Scoping
(1) As soon as possible after the decision to prepare an EIS, the district, in actions where the district is the proponent of an action, or the board, in all other actions, shall notify and inform the public and affected agencies that an EIS will be prepared and that scoping is beginning.
(2) The scoping process shall include, to the extent possible, affected federal, state and local agencies, the board, the proponent of the action, and other interested persons. The process may consist of meetings, hearings, workshops, surveys, questionnaires, or other appropriate methods or activities, and may be integrated with other public participation requirements.
(3) The scoping process shall be used to accomplish all of the following:
(a) Determine the scope and the significant issues to be analyzed in depth in the EIS.
(b) Identify and eliminate from detailed study the issues which are not significant or which have been covered by prior environmental review. This will narrow the discussion of these issues in the EIS to a brief presentation of why they will not have a significant effect on the human environment or a reference to their coverage elsewhere.
(c) Set a time for document preparation and opportunities for public involvement.

Wis. Admin. Code Technical College System Board § TCS 12.05

Cr. Register, April, 1987, No. 376, eff. 5-1-87.