Wis. Admin. Code Public Service Commission PSC 185.761

Current through November 25, 2024
Section PSC 185.761 - Alternative sample-testing plan for in-use meters
(1) As an alternative to testing 100% of meters that require testing under s. PSC 185.76, a utility may test a population sample equal to 25% of the total to be tested of each meter size. This test sample shall be a random selection of the total to be tested and each meter size test shall be conducted independently. If 10% or more of the test sample does not meet the accuracy requirements of s. PSC 185.35, the utility shall test all meters of that size in accordance with s. PSC 185.76.
(2) Meters testing inaccurately under sub. (1) shall be repaired prior to being returned to service. The test sample selected shall be rescheduled for testing under the intervals set forth in s. PSC 185.76(1). The meters not selected shall be rescheduled for testing at an interval not exceeding one-half the test intervals set forth in s. PSC 185.76(1).

Wis. Admin. Code Public Service Commission PSC 185.761

CR Register, January, 1997, No. 493, eff. 2-1-97.