Wis. Admin. Code Public Service Commission PSC 135.307

Current through October 28, 2024
Section PSC 135.307 - Inspection of materials addition [49 CFR 192.307]

After the text in 49 CFR 192.307, insert:

(1w) Detection of gouges and grooves. The field inspection provided on each job shall be suitable to reduce to an acceptable minimum the chances that gouged or grooved pipe will get into the finished transmission line or main. Inspection for this purpose just ahead of the coating operation and during the lowering in and backfill operation is required.

Wis. Admin. Code Public Service Commission PSC 135.307

CR Register, October, 1999, No. 526, eff. 11-1-99.