Current through October 28, 2024
Section PSC 134.28 - Meter testing(1) Each meter test of a diaphragm type meter with a capacity of 2,400 cubic feet per hour or less shall consist of one proving at a rate of flow of 15 to 30% of the rated capacity of that meter and one proving at a rate of flow at 90 to 120% of the rated capacity of the meter. The capacity of the meter for test purposes shall be the capacity at one-half inch water column differential pressure.(2) Each meter test of a diaphragm type meter having a capacity greater than 2,400 cubic feet per hour shall consist of one proving at a rate of flow of 15 to 30% of the rated capacity of that meter and one proving at a rate of flow of 90 to 120% of the rated capacity of the meter but not less than 2,500 cubic feet per hour. The capacity of the meter for test purposes shall be the capacity at one-half inch water column differential pressure.(3) Rotary meters shall be tested at 2 loads with the minimum load at 10% of rating by the use of a portable or volumetric meter or other approved proving devices, or be given a differential test. In the latter case an original test record shall be set up immediately after installation; future differential test results shall be recorded and compared with the original test record.(4) A test of an orifice meter shall consist of tests of the recording gauges, and the removal, inspection and measurement of the orifice.(5) Temperature-compensated gas displacement meters when tested shall be proved to a base temperature of 60° Fahrenheit.(6) Turbine-type meters shall be tested at 2 loads with the minimum load at 10% of rating by the use of a portable or volumetric meter or other approved proving devices, or be given a turbine blade, rotor and gear assembly spin test, either by manual or velocity rotation. Before a particular type turbine meter can be used, the manufacturer must file with and be accepted by the commission a minimum coasting time which will satisfactorily indicate the operating condition of the internal metering mechanism. For the spin test method a test record shall be set up; and the original and subsequent spin test results shall be recorded and compared with the specified minimum coasting time as filed with the commission for that type meter.Wis. Admin. Code Public Service Commission PSC 134.28
CR Register, February, 1959, No. 38, eff. 3-1-59; am. (3), Register, November, 1962, No. 83, eff. 12-1-62; CR (5), Register, January, 1965, No. 109, eff. 2-1-65; CR (6), Register, April, 1969, No 160, eff. 5-1-69; am. (1) and (2), Register, November, 1989, No. 407, eff. 12-1-89.