Section PSC 119.32 - Additional test

The public utility or applicant may, upon reasonable notice, re-test the DG facility installation after a failed test under s. PSC 119.30 or 119.31 or a disconnection under s. PSC 119.09. The party responsible for the re-testing shall bear the cost of the re-tests.

Wis. Admin. Code Public Service Commission PSC 119.32

CR 03-003: CR Register January 2004 No. 577, eff. 2-1-04.
Amended by, CR 22-077: am. Register April 29 No. 820, eff. 5/1/2024