Wis. Admin. Code Public Service Commission PSC 119.06

Current through October 28, 2024
Section PSC 119.06 - Modifications to the DG facility

DG facility by providing at least 20 working days of advance notice for a Category 1 DG facility, 40 working days for Category 2 DG facility, and 60 working days for a Category 3 or 4 DG facility. The applicant shall provide this notification by submitting a revised standard application form and such supporting materials as may be reasonably requested by the public utility. The applicant may not commence any material modification to the DG facility until the public utility has approved the revised application, including any necessary engineering review or distribution system study. The public utility shall indicate its written approval or rejection of a revised application within the number of working days shown in the table below. Upon completion of the application process, a new standard interconnection agreement shall be signed by both parties prior to parallel operation. If the public utility fails to respond in the time specified in Table 119.06-1, the completed application is deemed approved.

Table 119.06-1

Category

Export Capacity after Modification

Working Days for Utility's Response to Proposed Modifications

1

20 kW or less

20

2

Greater than 20 kW to 200 kW

40

3

Greater than 200 kW to 1 MW

60

4

Greater than 1 MW to 15 MW

60

Wis. Admin. Code Public Service Commission PSC 119.06

CR 03-003: CR Register January 2004 No. 577, eff. 2-1-04.
Amended by, CR 22-077:Register April 29 No. 820, eff. 5/1/2024.