Wis. Admin. Code Public Service Commission PSC 113.0812

Current through October 28, 2024
Section PSC 113.0812 - Accuracy of demand meters

In this section, "meter" or "meters" may refer to metering system(s).

(1) A demand meter, demand register, or demand attachment used to measure customer's service shall:
(a) Be in good mechanical and electrical condition.
(b) Have proper constants, indicating scale, contact device and resetting device.
(c) Not register at no load.
(d) Be accurate to the following degrees:
1. Curve drawing meters which record quantity time curves and integrated-demand meters shall be accurate to within plus or minus 2.0% of full scale throughout their working range. Timing elements measuring specific demand intervals shall be accurate to within plus or minus 2.0% and the timing elements which serve to provide a record of the time of day when the demand occurs shall be accurate to within plus or minus 4 minutes in 24 hours.
2. Lagged-demand meters shall be accurate to within plus or minus 4% of full scale at final indication.
(2) The overall accuracy of demand metering installations utilizing pulse-initiator and pulse-recorder equipment shall be acceptable when the monthly kilowatt-hours calculated from the pulse count do not differ from the corresponding kilowatt-hour meter registrations by more than the kilowatt-hour constant of the meter, or 2%, whichever is greater. The timing element error shall not be more than plus or minus 4 minutes per day.
(3) When a timing element also serves to keep a record of the time of day at which the demand occurs, it shall be corrected if it is found to be in error by more than plus or minus 4 minutes per day.

Wis. Admin. Code Public Service Commission PSC 113.0812

CR Register, July, 2000, No. 535, eff. 8-1-00.