Wis. Admin. Code Public Service Commission PSC 113.0805

Current through November 25, 2024
Section PSC 113.0805 - Tamper-resistant equipment

Where electrical energy has been diverted or the utility's equipment for measuring the service or controlling a customer's load has been interfered with, the utility may require the customer to install entrance and service equipment to prevent current diversion or interference with the metering or control equipment.

Wis. Admin. Code Public Service Commission PSC 113.0805

CR Register, July, 2000, No. 535, eff. 8-1-00.

See s. PSC 113.0808.

Care should be taken in determining the existence of diversion and amount of energy diverted. In case check-meters are used, the possibility of grounds between meters, normal meter inaccuracies and incorrect connections of meters should not be over-looked. The requirements of the Wisconsin state electrical code for entrances should effectively prevent such diversion. Attention is directed to ss. 939.32 and 943.20, Stats.