Wis. Admin. Code Department of Safety and Professional Services SPS 320.18

Current through September 30, 2024
Section SPS 320.18 - Building product approvals
(1) VOLUNTARY APPROVAL.
(a) Materials, equipment and products regulated by this code may receive a written approval from the department indicating code compliance.
(b)
1. Approval of materials, equipment and products shall be based on sufficient data, tests and other evidence that prove the material, equipment or product is in compliance with the standards specified in this code.
2. Tests, compilation of data, and calculations for materials, equipment and products shall be conducted by a qualified independent third party.
(2) ALTERNATE APPROVAL.
(a) Materials, equipment and products which meet the intent of this code and which are not approved under sub. (1) shall be permitted if approved in writing by the department.
(b)
1. Approval of materials, equipment and products shall be based on sufficient data, tests and other evidence that prove the material, equipment or product meets the intent of the standards specified in this code.
2. Tests, compilation of data, and calculations for materials, equipment and products shall be conducted by a qualified independent third party.
(3) EXPERIMENTAL APPROVAL.
(a) The department may allow use of an experimental material, equipment or product for the purpose of proving compliance with the intent of this code.
(b) The department may require the submission of any information deemed necessary for review.
(c) The department may limit the number of applications it will accept for approval of experimental materials, equipment or products.
(d) Installations of a material, equipment or product under an experimental approval shall comply with all of the following:
1. Plans detailing the installation for each project where the experimental material, equipment or product is to be used shall be submitted to the department.
2. A copy of the experimental approval shall be attached to the submitted plans and approved plans.
3.
a. A letter of consent from the owner of the installation shall be attached to the submitted plans and approved plans.
b. The letter under subd. 3. a. shall acknowledge that the owner has received and read a copy of the experimental approval and is in compliance with all conditions of the approval.
4. A person responsible for construction of the project shall be designated in writing by the owner.
5. The person designated as responsible for the construction of the project shall, upon completion of construction, certify in writing to the department that the installation is in compliance with the experimental approval, approved plans, specifications and data.
(e)
1. Any onsite inspections shall be performed by the department, or other person authorized by the department, at time intervals as specified by the department, but not less than once a year. The inspector shall write an inspection report.
2. The department may assess a fee for each inspection conducted under subd. 1.
(f) Five years and 6 months after the date of the completed installation, the department shall order the removal of the experimental material, equipment or product, or issue an approval for the material, equipment or product.
(g) Paragraphs (e) and (f) do not apply to an experimental system if this code is revised to include or enable the experimental system to conform to the intent of this code.
(4) REVIEW, APPROVAL AND REVOCATION PROCESSES.
(a)
1. Upon receipt of a fee and a written request, the department may issue an approval for a material, equipment or product.
2. The department shall review and make a determination on an application for approval after receipt of all forms, fees, plans and information required to complete the review.
3. For voluntary and alternate approvals, a determination shall be made within 40 business days of receipt of all required materials.
4. For an experimental approval, a determination shall be made within 6 months of receipt of all required materials.
(b)
1. The department may include specific conditions in issuing an approval, including an expiration date for the approval.
2. Violations of the conditions under which an approval is issued shall constitute a violation of this code.
(c) If the department determines that the material, equipment or product does not comply with this code or the intent of this code, or that an experimental approval will not be issued, the request for approval shall be denied in writing.
(d) If an approved material, equipment or product is modified, the approval shall be considered null and void, unless the material, equipment or product is resubmitted to the department for review and approval is granted.
(e)
1. The department may revoke or deny an approval of a material, equipment or product for any false statements or misrepresentations of relevant facts or data, unacceptability of a third party providing information, or as a result of material, equipment or product failure.
2. The department may re-examine an approved material, equipment or product and issue a revised approval at any time.
(f) The department may revoke an approval if the department determines that the material, equipment or product does not comply with this code or the intent of this code due to a change in the code or department interpretation of the code.
(g) An approval issued by the department may not be construed as an assumption of any responsibility for defects in design, construction or performance of the approved material, equipment or product nor for any damages that may result.
(h) Fees for the review of a material, equipment or product under this section and any onsite inspections shall be submitted in accordance with ch. SPS 302.
(5) UNGRADED OR USED MATERIALS.
(a) Ungraded or used building materials may be used or reused as long as the material possesses the essential properties necessary to achieve the level of performance required by the code for the intended use.
(b) The department or the municipality enforcing this code may require tests in accordance with sub. (1) or (2).

Wis. Admin. Code Department of Safety and Professional Services SPS 320.18

Cr. Register, November, 1979, No. 287, eff. 6-1-80; cr. (3), Register, February, 1985, No. 350, eff. 3-1-85; am. (1), Register, November, 1995, No. 479, eff. 12-1-95; correction in (1) (intro.) made under s. 13.93(2m) (b) 7, Stats., Register, October, 1996, No. 490; r. and recr., Register, September, 2000, No. 537, eff. 10-1-00; correction in (4) (h) made under s. 13.92(4) (b) 7, Stats., Register December 2011 No. 672.