Wis. Admin. Code Department of Safety and Professional Services SPS 327.18

Current through December 30, 2024
Section SPS 327.18 - Appeals of orders, determinations, and for extension of time
(1) APPEALS OF ORDERS AND DETERMINATIONS BY A MUNICIPALITY EXERCISING JURISDICTION. Appeals of order or determination of a municipality exercising jurisdiction under this code, including denials of application for permits, shall be made in accordance with the procedure set out in ch. 68, Stats., prior to making an appeal to the department, except as provided in sub. (2).
(2) APPEALS OF FINAL DETERMINATIONS BY A MUNICIPALITY EXERCISING JURISDICTION. Appeals of final determinations by municipalities shall be made to the department after the procedures prescribed in ch. 68, Stats., have been exhausted. All appeals to the department shall be in writing stating the reason for the appeal. All appeals shall be filed with the department within 10 business days of the date the final determination is rendered under ch. 68, Stats. The department shall render a written decision on all appeals within 60 business days of receipt of all calculations and documents necessary to complete the review.

Note: Chapter 68, Stats., provides that municipalities may adopt alternate administrative appeal procedures that provide the same due process rights as ch. 68, Stats. Municipalities having adopted such alternate procedures may follow those alternate procedures.

(3) APPEALS OF ORDERS AND DETERMINATIONS BY THE DEPARTMENT. Appeals of orders or determinations of the department made pursuant to the provisions of this code, including denials of application for permits, shall be in accordance with the procedure set out in s. 101.02(6) (e) to (i) and (8), Stats. The department shall review and make a determination on an appeal of an order or determination within 60 business days of receipt of all calculations and documents necessary to complete the review.
(4) EXTENSIONS OF TIME.
(a) The time for correction of cited orders as set out in s. SPS 327.11 shall automatically be extended in the event that an appeal of the orders is filed. The extension of time shall extend to the termination of the appeal procedure and for additional time as the department or municipality administering and enforcing this code may allow.
(b) The department or municipality administering and enforcing this code may grant additional reasonable time in which to comply with a violation order.

Wis. Admin. Code Department of Safety and Professional Services SPS 327.18

Adopted by, EmR1703: emerg. cr., eff. 2-6-17; CR 17-017: cr. Register March 2018 No. 747, eff. 4/1/2018