Wis. Admin. Code Department of Safety and Professional Services SPS 308.12

Current through August 26, 2024
Section SPS 308.12 - Permits
(1) GENERAL. Before an excavation of a shaft may be commenced, a permit shall be obtained from the department. As provided by s. 101.15(2) (c), Stats., this section does not apply to shafts less than 50 feet in depth wherein persons are not employed, shafts not equipped with power driven hoists used for hoisting persons in and out of shafts, or shafts not covered with a flammable building.
(2) APPLICATION FOR PERMIT. Application for a shaft excavation permit shall be made on forms provided by the department together with the payment of the permit fee.

Note: The mine shaft excavation permit application is available from the Department's Division of Industry Services at P.O. Box 7302, Madison, WI 53707-7302; by email at dsps@wisconsin.gov; by telephone at (608) 266-2112, (877) 617-1565, or 411 (Telecommunications Relay); or at the division's website at http://dsps.wi.gov/programs/industry-services.

(3) PLANS AND SPECIFICATIONS. Plans and specifications shall be submitted with the application for a shaft excavation permit which show that the shaft, excavation and workings are in compliance with this chapter.
(4) PERMIT PROCESSING TIME. The department shall review and make a determination on a shaft excavation permit application within 30 business days of receiving the required information and fees.

Wis. Admin. Code Department of Safety and Professional Services SPS 308.12

Cr. Register, May, 2001, No. 545, eff. 6-1-01.
Amended by, CR 17-034: am. (2), Register March 2018 No. 747, eff. 4/1/2018