Wis. Admin. Code Department of Safety and Professional Services SPS 362.0909

Current through October 28, 2024
Section SPS 362.0909 - Smoke control systems
(1) INSPECTION AND TEST REQUIREMENTS. Substitute the following wording for the requirements in IBC section 909.3: In addition to the ordinary inspection and test requirements that buildings, structures and parts thereof are required to undergo, smoke control systems subject to the provisions of IBC section 909 shall undergo inspections and tests sufficient to verify the proper commissioning of the smoke control design in its final installed condition. The design submission accompanying the construction documents shall clearly detail procedures and methods to be used and the items subject to such inspections and tests. Such commissioning shall be in accordance with generally accepted engineering practice and, where possible, based on published standards for the particular testing involved.
(2) INSPECTIONS FOR SMOKE CONTROL. Substitute the following wording for the requirements in IBC section 909.18.8: Smoke control systems shall be tested by a qualified agency.
(3) SCOPE OF TESTING. Substitute the following wording for the requirements in IBC section 909.18.8.1: Inspections shall be conducted in accordance with the following:
(a) During erection of ductwork and prior to concealment for the purposes of leakage testing and recording of device location.
(b) Prior to occupancy and after sufficient completion for the purposes of pressure-difference testing, flow measurements, and detection and control verification.
(4) QUALIFICATIONS. Substitute the following wording for the requirements in IBC section 909.18.8.2: Inspection agencies for smoke control shall have expertise in fire protection engineering, mechanical engineering and certification as air balancers.
(5) REPORTS. Substitute the following wording for the requirements in IBC section 909.18.8.3: A complete report of testing shall be prepared. The report shall include identification of all devices by manufacturer, nameplate data, design values, measured values and identification tag or mark. The report shall be reviewed by the responsible registered design professional and, when satisfied that the design intent has been achieved, the responsible registered design professional shall seal, sign and date the report.
(6) REPORT FILING. Substitute the following wording for the requirements in IBC section 909.18.8.3.1: A copy of the final report shall be maintained and made available to the building official upon request.

Wis. Admin. Code Department of Safety and Professional Services SPS 362.0909

CR 00-179: cr. Register December 2001 No. 552, eff. 7-1-02, CR 06-120: renum. (5) and (6) to be (6) and (7), cr. (5) Register February 2008 No. 626, eff. 3-1-08.; CR 10-103: r. (7) Register August 2011 No. 668, eff. 9-1-11.