Wis. Admin. Code NR § 500.065

Current through May 28, 2024
Section NR 500.065 - License issuance
(1) INITIAL APPLICATIONS. The department shall make a determination on an initial application for a solid waste facility license within 65 business days of receipt of all of the information specified in s. NR 500.06. If a determination is not made on the application within 65 business days, the department shall refund the license application fee paid by the applicant.
(2) RENEWALS. The department shall make a determination on a license renewal application for a solid waste facility license within 65 business days of receipt of all of the information specified in s. NR 500.06, or by the end of the current license period, whichever occurs later. If a determination is not made within these time constraints, the department shall refund the license renewal application fee paid by the applicant.

Wis. Admin. Code Department of Natural Resources § NR 500.065

Cr. Register, September, 1998, No. 513, eff. 10-1-98.