Wis. Admin. Code Department of Natural Resources NR 747.70

Current through October 28, 2024
Section NR 747.70 - Monitoring the progress of the scope of work in the bid
(1) NOTIFICATION OF PROGRESS.
(a) The consulting firm holding the contract required in s. NR 747.69(1) (a) shall report to the department, in a format prescribed by the department, the progress toward completing the scope of work defined in the bid specifications, at each of the following points:
1. Three months after entering into the contract.
2. Twelve months after beginning the work in the successful bid, except as provided in subd. 6.
3. Twelve months after submitting the previous report required under this subsection, except as provided in subd. 6.
4. No later than 10 days after encountering a change in circumstances, as specified in sub. (3).
5. At any other frequency directed by the department.
6. No later than 30 days after completing the work.
(b) For occurrences that are not covered under s. 101.144(2) (b), Stats., the department shall send the DNR a copy of the reports received under par. (a).

Note: This paragraph is no longer effective and is subject to future repeal. Section 101.144, Stats., was repealed by 2013 Wis. Act 20. The "department" in this paragraph refers to the department of safety and professional services, which no longer has responsibility for occurrences under this section.

Note: See s. NR 747.71(5) for special requirements for existing sites.

(2) FAILURE TO MAKE PROGRESS. If the department determines that the consulting firm is failing to make adequate progress to complete the scope of work defined in the bid specifications for an amount not exceeding the reimbursement cap determined under s. NR 747.68(7), the department shall so notify the responsible party and may reduce the reimbursement to accurately reflect the work completed.

Note: See s. NR 747.71(5) for special requirements for existing sites.

(3) CHANGE OF CIRCUMSTANCES.
(a) For occurrences under the direction of the department, the department may review and modify the reimbursement cap, and may reinitiate the public bidding process in s. NR 747.68, based on a change in circumstances, if any of the following have occurred:
1. Substantial new contamination has been discovered on the site. Substantial contamination must increase remediation costs to either obtain closure or complete a defined scope of work. New contamination is contamination not previously identified, such as contamination in a broader area or deeper depth than previously identified.
2. Abnormal weather, previously unknown geologic conditions, or previously unknown subsurface structures have been encountered that directly affect the activities described in the least costly qualified bid identified under s. NR 747.68(3).
(b) For occurrences under the direction of the department, the department may review and modify the reimbursement cap, and the department may reinitiate the public bidding process in s. NR 747.68, based on a change of circumstances, if any of the events in par. (a) 1. and 2. have occurred.

Note: See s. NR 747.71(5) for special requirements for existing sites.

(4) DISQUALIFICATION FROM FURTHER WORK ON A PROJECT.
(a)Grounds for disqualification. The department may disqualify any individual or firm from performing further work on a project, if the individual or firm has done any of the following:
1. Failed to complete a substantive portion of the defined scope of work within the corresponding portion of the reimbursement cap.
2. Failed to complete the scope of work in a bid in a timely manner.
3. Failed to meet requirements in department rules on the project.
4. Failed to do either of the following:
a. Pay subcontractors within a contracted timeline, after receiving payment for them.
b. Obtain lien waivers on or before the date of the final payment by the responsible party or the PECFA program, from all subcontractors paid under subd. 4. a.
5. Failed to execute a contract with a responsible party as required in s. NR 747.69(1).
6. Failed to commence work within 45 days after executing a contract, as required in s. NR 747.69(3).

Note: See s. NR 747.71(5) for special requirements for existing sites.

(b) In making disqualification decisions under this section, the department shall only excuse failures that are shown to be due to factors which are beyond the control of a bidding individual or firm, such as a responsible party's inability to obtain financing.
(c)Period of disqualification. The period of disqualification shall be 6 months for the first disqualification, 12 months for the second disqualification, and 24 months for any successive disqualification.

Note: The department may consider disqualification from further work as a contributing factor when applying other disciplinary actions to any individual or firm.

(d)Written notice of disqualification. The department shall provide written notification to any individual or firm disqualified from performing further work on a project. The notification shall specify the reasons for the disqualification, the period of the disqualification, and the right to appeal the department's decision. The notification shall inform the disqualified party that costs for any work on the occurrence during the disqualification, except as otherwise authorized by the department, will not be reimbursed.
(e)Appeals by disqualified individuals or firms.
1. An individual or firm that receives a notice of disqualification under this section may appeal as provided in s. NR 747.53.
2. The department shall hold a hearing for an appeal filed under subd. 1. no later than 30 days after receipt of the appeal.
(f)Rebidding or selection of next-lowest, qualified bid. Where an individual or firm has been disqualified under this section, the department may either redirect the scope of work through the entire public bidding process in s. NR 747.68, or reinitiate that process at the bid evaluation stage in s. NR 747.68(3).
(g)Corrective action by disqualified individual or firm. The department may require an individual or firm that has previously been disqualified to take corrective action specified by the department, to protect owners or operators and the PECFA fund from failure to carry out the work specified in the public bidding process in s. NR 747.68.

Wis. Admin. Code Department of Natural Resources NR 747.70

CR 04-058: cr. Register February 2006 No. 602, eff. 5-1-06; correction in (1) (a), (2), (3) (a) (intro.), 2., (b), (4) (a) 5., 6., (e) 1., (f), (g) made under s. 13.92(4) (b) 7, Stats., Register December 2011 No. 672; corrections in (1) (a) (intro.), (b), (2), (3) (a) (intro.), 2., (b), (4) (a) 3., 5., 6., (e) to (g) made under s. 13.92(4) (b) 6, 7., Stats., Register October 2013 No. 694.