Wis. Admin. Code Department of Natural Resources NR 193.18

Current through August 26, 2024
Section NR 193.18 - Grant payments

The department may make payments to the grantee, including advance payments, escrow payments and reimbursements, in the following manner:

(1) Grants awarded under this chapter are generally administered on a reimbursement basis. A grantee shall incur and pay all costs and invoiced work completed before requesting a partial or final payment from the department. A grantee shall submit to the department a request for reimbursement on forms designated by the department at a frequency determined by the department and specified in the grant agreement.
(2) The department may distribute one grant advance, with a maximum amount determined per subprogram using the percentage identified in Table 1 under s. NR 193.05. The grantee may request a grant advance at the same time the grantee returns a signed grant agreement to the department.
(3) The department may only reimburse for eligible project costs incurred during the grant period, except when otherwise approved by the department in writing. For management grants, land acquisition grants notwithstanding, a grantee may request one partial payment per year. The total of all partial payments issued by the department may not exceed 90% of the total grant award. Education and Planning grants are not eligible for partial payments. Table 2 under sub. (5) summarizes partial payments by grant program. A request for partial payment shall be submitted along with a progress report detailing activities that have taken place during the time period for which the grantee is seeking reimbursement and is subject to approval by the department.
(4) A request for final payment shall be submitted no later than 6 months after the end of the grant period. Final payment requests shall be accompanied by a final report detailing activities that have taken place during the entire project period and documentation for the costs being claimed. The final payment may not be issued by the department until final costs have been reviewed, final reports have been approved, required audits have been completed successfully, and the department has made a determination that the grant agreement has been satisfactorily fulfilled.
(5) All project costs are subject to a post-audit process that may take place after partial and final payments are issued by the department. If a determination is made that payments were made in error, the grantee may be required to make a repayment to the department.

TABLE 2

Surface Water Grant Program Payment Table

This table summarizes eligibility for partial payments, the maximum frequency of payments, the maximum number of partial payments allowed during the life of the grant, and the percentage of the grant award that is required to be retained for final payment for each subprogram under this chapter.

Grant Category

Grant Type

Partial Payments Allowed

Frequency of Partial Payments

Maximum Number of Partial Payments

Percentage of Grant Award Retained for Final Payment

Education and Planning Grants

All Education and Planning Grants

No

Not applicable

Not applicable

25%

Management Grants

Lake & River Fee Simple Land and Easement Acquisition

No

Not applicable

Not applicable

Remaining associated costs

Wetland Restoration Incentives

No

Not applicable

Not applicable

0%

All other Management Grants

Yes

1 per year

4

10%

Wis. Admin. Code Department of Natural Resources NR 193.18

Adopted by, CR 19-078: cr. Register May 2020 No. 773, eff. 6-1-20; correction in (2) made under s. 35.17, Stats., Register May 2020 No. 773, eff. 6/1/2020